In light of the Building Safety Act 2022, construction professionals and safety specialists must be thoroughly equipped to meet the rigorous demands of their forthcoming projects. It is essential to navigate three pivotal Gateways to ensure buildings not only uphold superior standards but also adhere to strict safety regulations. This guide outlines the critical stages required to achieve full compliance, safeguarding the well-being of all occupants.
The first crucial milestone is Gateway 1, where fire safety takes precedence.
Applicability: This phase applies to High-Risk Buildings (HRBs), defined as structures exceeding 18 metres in height, consisting of seven or more storeys, or housing multiple residential units.
Key Requirements:
As the project advances, Gateway 2 must be cleared before construction begins.
Requirements: A Building Control Application must be submitted to the Building Safety Regulator (BSR) to confirm that the design complies with all necessary safety regulations.
Essential Documentation:
Additional Provisions: A Change Control Plan must be maintained, and compliance with Mandatory Occurrence Reporting (MOR) protocols is required to address any unforeseen issues that may arise during construction.
Upon the completion of construction, Gateway 3 ensures that all requisite safety measures are fully implemented prior to occupancy.
Final Requirements:
Final Approval: Once the Building Safety Regulator (BSR) issues a Completion Certificate, the building will be deemed fit for occupancy.
Successfully navigating the Gateway process is a multifaceted and rigorous task. However, by adhering meticulously to these requirements, construction professionals can ensure that their buildings meet the highest safety standards, safeguarding the well-being of all future occupants. The journey to a compliant and secure building begins with dedicated attention to each phase of the Gateway process.